A dated Alberta energy project shortlist with reported stages, source links, equipment lessons and a printable business-readiness checklist.
Inventory fields checked 2026-10-14. Stages, costs and schedules are attributed to Alberta Major Projects and are not independently confirmed operating facts.
Pipelines · Inventory: Under construction
Yellowhead Mainline
An industrial natural-gas supply project linking the Peers area and Fort Saskatchewan region. Its intended role is to serve new industrial demand and other customers; planned capacity is different from gas actually flowing.
Central Alberta / Industrial Heartland · Canadian Utilities Inventory cost: $2.9 billion CAD · Schedule: 2026–2027
Watch construction milestones and commissioning separately. The inventory's September groundbreaking reference differs from the government's October 13 ceremony announcement; neither alone establishes an in-service date.
Generic teaching equipment, not this developer's facility design.
Petrochemicals · Inventory: Under construction
Fort Saskatchewan Path2Zero
A petrochemical expansion and modernization project at Fort Saskatchewan. It connects Alberta feedstocks with polyethylene and ethylene-derivative manufacturing rather than finished transportation fuels.
The inventory records a January 2026 announcement moving phase-one completion to 2029 and phase two to 2030. Treat these as reported plans, with construction stage distinct from operational readiness.
Generic teaching equipment, not this developer's facility design.
Oil sands · Inventory: Under construction
Kearl in-pit tailings project
A tailings-management project associated with the existing Kearl mine. The reported transition is from surface storage toward use of a mined-out pit, rather than a newly announced oil-sands mine.
A listed schedule is not evidence of completion or environmental performance. Follow operator updates and regulator records for actual milestones, water management and closure obligations.
Generic teaching equipment, not this developer's facility design.
Carbon management · Inventory: Under construction
Polaris carbon capture
A capture project associated with Shell's Scotford refinery and chemicals operations. Capture equipment and the underground storage system have different functions and should be assessed separately.
Industrial Heartland · Shell Inventory cost: Not disclosed in inventory · Schedule: 2024–2028
The inventory reports a June 2024 investment decision. Announced design capacity is not measured capture, and captured volume is not the same as independently verified permanent storage.
Generic teaching equipment, not this developer's facility design.
Carbon management · Inventory: Under construction
Atlas carbon storage hub
An industrial CO₂ storage hub east of Edmonton. Its connection to capture projects illustrates why a capture plant, transport system and geological storage site are related but separate parts of the chain.
Industrial Heartland · Shell / ATCO EnPower joint venture Inventory cost: Not disclosed in inventory · Schedule: 2025–2028
The inventory reports a sequestration agreement and investment decision. Verify project-specific approvals, injection readiness and monitoring evidence rather than treating an agreement as proof of current storage.
Generic teaching equipment, not this developer's facility design.
Pipelines · Inventory: Completed
Key Access Pipeline System
A liquids pipeline system connecting production regions with the Fort Saskatchewan processing and storage area. Condensate and a natural-gas-liquids mixture serve different downstream uses.
The inventory marks the construction project completed. This does not measure current throughput or establish open capacity, tariffs or a present supplier contract opportunity.
Generic teaching equipment, not this developer's facility design.
Build in Alberta: research checklist
Define your Alberta project
Write down the product or service, customer, feedstock, capacity range, utilities and logistics you would need. Separate your assumptions from documented site capabilities.
Compare regions before choosing a site
Compare Wood Buffalo, the Industrial Heartland and northwest Alberta using actual transport connections, municipal land-use information, workforce needs and utility enquiries.
Establish the decision and approval stage
Record the proponent, source date and what has actually been approved. An announced investment, regulator decision, construction start and operating facility are different milestones.
Plan relationships and responsibilities
Identify the appropriate municipality, Indigenous communities and potential business partners. Commercial partnerships do not replace any applicable Crown consultation or regulatory process.
Build a transparent scenario
Record prices, FX, transport, diluent, operating costs and capital assumptions. Use the toolbench for learning and sensitivity checks; obtain qualified project-specific financial and regulatory work.
Check the actual supplier channel
Use the developer's own procurement process. Confirm scope, timing, vendor requirements and payment terms directly; a directory entry is not an open tender or a promise of work.
Directory entries are not open tenders. Read the inventory methodology. JavaScript enables filtering, browser watchlists and print controls.